Hi Folks, * CDL has the network cable to support building 9010 in place. We could use a hand running the network cables from the VCF area into the next "H" section (9010B) Would be a total of three cable, two for cameras in the hallway, and one to the firewall in the VCF rack * Other projects include cutting unistrut and mounting the rack on the brick wall in 9010B. We scheduled for December 21st, starting around 11:00 AM Off list replies prefer to prese the S/N radio of the list. Martin Flynn