Quick update:
1. VCF and CDL (Ken, Mona, Stephen, and myself) were working on the
network prep for VCF-East. Ken and Mona wrapped up the installation
of the fiber hangers on 9059 (this is for the fiber to 9032A) ,
Stephen and myself prepped the new data switch for 9032A.
2. The whole team worked on the data rack in the hotel basement as prep
for upgrading the first floor WiFi. Picture of the last two
weekends work in the hotel at
http://compdecon.org/wp-content/uploads/2021/08/img_1382.jpeg
3. Our friends at Ubiquiti sent two more UniFi access points for the
9032A meeting room (UAP-AC-PRO-E-US)